2017.04.29 - Bank Holiday Weekend Job List

Today is the start of a three-day weekend due to the May Bank Holiday on Monday. This means that I should be able to get a fair bit of work done. So the list, in no particular order is as follows:

  • Bobstay stem fitting
  • Cabin bottom boards
  • Cast lead
  • Cockpit bottom boards
  • Eye bolt on gaff
  • Fire tray
  • Flag mount
  • Reefing point boom hardware
  • Shape tiller
  • Slot for outhaul sheave in boom
  • Suspend bowsprit
  • Suspend quant
  • Whisker shrouds

Of these, the flag mount can only be done if the bolts are in the post today.

Priority-wise the list should look something like this:

Highest:

  • Bobstay stem fitting
  • Shape tiller
  • Eye bolt on gaff
  • Slot for outhaul sheave in boom
  • Reefing point boom hardware

Medium:

  • Whisker shrouds
  • Suspend bowsprit
  • Suspend quant
  • Cockpit bottom boards

Lowest:

  • Cabin bottom boards
  • Fire tray
  • Cast lead
  • Flag mount

Should be an interesting weekend.